Scotland Co. Water Main

Project Info

The project consisted of installation of approximately 73,000 feet of 8” transmission water main and Booster Pump Station upgrades as well as the installation of a new remote read metering system. The new main and pump station improvements allow the District to better feed the system and improve the hydraulic operating conditions of their existing elevated water storage tank. A new cellular read metering system was installed and included replacing all 1,350 meters in the District.

Funding

MDNR SRF Loan

Cost

$1,430,000

Client

Scotland County Consolidated Public Water Supply District #1 – Memphis, MO